Install
GRID Power Act
A bill to require the Federal Energy Regulatory Commission to reform the interconnection queue process for the prioritization and approval of certain projects, and for other purposes.
- Introduced
- Committee
- Passed Senate
- Passed House
- To President
- Became law
Summary
Guaranteeing Reliability through the Interconnection of Dispatchable Power Act or the GRID Power Act
This bill requires the Federal Energy Regulatory Commission (FERC) to issue and periodically review a rule that revises the approval process for interconnection requests of generating units that produce electricity to prioritize dispatchable power projects (e.g., certain fossil fuel projects).
Under the bill, dispatchable power generally refers to an electric energy generation resource, such as a generating unit that produces electricity from fossil fuels, capable of providing known and forecastable electric supply in time intervals necessary to ensure grid reliability. Currently, FERC receives interconnection requests from those projects and other generating units, such as units that produce electricity from renewable energy. Interconnection requests are requests from generating units to connect to the high voltage transmission lines of the electric grid.
First, the rule must address the efficiency and effectiveness of the existing procedures for processing interconnection requests to ensure that new dispatchable power projects that improve grid reliability and resource adequacy can interconnect to the electric grid quickly, cost-effectively, and reliably.
Second, the rule must revise the pro forma Large Generator Interconnection Procedures, and the pro forma Large Generator Interconnection Agreement as appropriate, to authorize transmission providers to submit proposals to FERC to prioritize new dispatchable power projects that will improve grid reliability and resource adequacy by assigning those projects higher positions in the interconnection queue of the provider. FERC must review and approve or deny such proposals within 60 days after the proposal is submitted.
Summary by the Congressional Research Service, Library of Congress.
Actions
- Sep 30, 2026 Committee on Energy and Natural Resources. Ordered to be reported without amendment favorably.
- Apr 15, 2026 Committee on Energy and Natural Resources Subcommittee on Energy. Hearings held. With printed Hearing: S.Hrg. 119-366.
- Feb 6, 2025 Read twice and referred to the Committee on Energy and Natural Resources.
- Feb 6, 2025 Introduced in Senate
Congressional and federal records come from official public sources: the House Clerk, the U.S. Senate, GovInfo and the Library of Congress (bill status), the Federal Register, and the congress-legislators project. They are copied on a schedule and may lag the official record by a few hours; the official sources govern. News and coverage counts are drawn from the 4Conservative index and reflect what the press published, not 4Conservative's views. Nothing here is an endorsement of any candidate, party or position. Terms of use.